How long may decisions take in an ERP project?
How fast an ERP project runs is decided not by the code, but by the pace of decisions.
Contents
A senior-led conversation gets to the heart of your situation.
Set a decision service level: open project decisions belong made within one to three weeks. Anything beyond that is not a scheduling problem but the earliest and most reliable warning sign of a governance problem. An ERP project moves at the speed of its decisions: if a single question stays open for three weeks, all dependent work piles up behind it, and one delay quickly becomes five, because each team waits on the next. The service level is the simplest remedy: establish that every open decision is made within one to three weeks, and make visible who makes it. If it is missed regularly, that is not a slip but a finding about your governance. The advantage of this measure: it costs nothing and cannot be gamed. Unlike a percentage complete, a decision has either been made or it has not.
Why does decision speed determine project success?
An ERP project moves at the speed of its decisions. If a single question stays open for three weeks, all the work depending on it piles up behind it. One delay quickly becomes five, because every team is waiting on the next.
The decision service level is the simplest instrument against that: establish that every open decision is made within one to three weeks, and make visible who makes it. If that level is regularly missed, that is not a slip but a finding about your governance.
The advantage of this measure is that it costs nothing and cannot be manipulated. Unlike a percentage complete, which can be estimated at will, an open decision has either been made or it has not. That is why it is the one figure that ought to appear in every status report, even where nobody asks for it.
Why is decision latency an early indicator of governance problems?
Long decision paths reveal missing governance before the budget or the date visibly tips. Whoever watches the decision latency sees the problem weeks earlier than in the traffic-light report. The frequent cause is rarely capacity:
- No one is allowed to decide bindingly, the role is not named.
- The person who would be allowed does not have enough insight into the trade-offs.
- Open items are settled without a fixed rhythm, everyone waits for everyone.
Both are governance, not a shortage of people. The lever is correspondingly simple: a named decision-maker per subject area, a decision log, and a fixed rhythm in which open points actually get settled. Control stays on your side.
If decisions regularly sit for too long at your company, that is rarely coincidence. Let us look in a conversation at where exactly the steering is stuck, with Business Central as home.
“
A project moves at the speed of its decisions, not of its meetings.
Frank Maier, founder of DGP
Frequently asked questions
Briefly asked
How fast should decisions be made in an ERP project?
Open project decisions belong made within 1 to 3 weeks. That requires a named decision-maker per topic area and a fixed rhythm in which open items are settled.
Why is decision time an early indicator of governance problems?
Because long decision paths reveal missing control before budget or schedule visibly tip. Decision latency warns weeks earlier than any traffic-light report.
How fast should decisions be made in an ERP project?
Operational questions within days, scope and budget questions within two weeks. Anything left longer costs team performance and schedule. A fixed decision cadence with named decision-makers belongs in every project charter.
Related
Related questions
Before the project
ERP selection: criteria, approach and checklist
The ten criteria that really decide, and the approach in five steps.
18.08.2026
Read →Before the project
What to look for in ERP selection when AI is the yardstick?
When AI is the yardstick, the selection questions change. Five criteria.
01.09.2026
Read →Before the project
What has to be decided before a Business Central project starts?
Sponsor, goals and governance have to be in place before the kick-off.
18.08.2026
Read →Where does your project really stand?
At DGP you speak with an experienced consultant, not with a sales team.
Stay on top of things without tracking everything yourself.
Once a month, Frank Maier puts into context what is moving in the ERP world. Plus the invitation to the next live webinar.
About one email a month. Unsubscribe at any time with one click. Privacy policy